CASE STUDY

Neerabup Ground Water Treatment Plant

Butterfly Valves

Water Corporation WA’s Neerabup Groundwater
Treatment Plant was expanded in 2020 to provide 50% increased capacity, to a total of 150 million litres of water per day. The $52 million turnkey project was delivered by the SACYR Westforce Construction Joint Venture, including engineering, construction and commissioning.

Flocontrol worked closely with SACYR WF JV to deliver the complete butterfly valves package, including manual and actuated valves and our top-tier, vulcanised butterfly valves approved for water service.

We tagged and tracked every valve at each step of the project, working closely with both manufacturers and our Water Corporation to ensure on-time project delivery, especially during the challenging months of COVID-19.

Throughout the project, we achieved successful project deliveries and commissioning, including third-party witness function testing. We also provided site support to ensure smooth installation and commissioning. Flocontrol is engaged with SACYR WF JV on subsequent projects and looks forward to many successful endeavours.